23 Haziran 2010 Çarşamba

23/06/2010





Remaining pieces are brought to site & partial temporary construction is made to spot possible problems and let the pieces dry

22/06/2010


Grouting of the holes & protective painting

21/06/2010


Elements fixed to the ground

10 Haziran 2010 Perşembe

Model at site

08/06/2010 model

Newest model that includes the production details. Elements are produced from multiple parts as in the real case.

4 Haziran 2010 Cuma

04/06/2010 model review


to clarify construction method and sequence, we produced a new model at 1/10 scale

3 Haziran 2010 Perşembe

03/06/2010 preparation of the site



second levelling concrete was poured




to form cavities for the placement of the structural members, a formwork was prepared and placed on the site


first levelling concrete was poured

02 June 2010


we started the work with the modification of the site